tamarac,#2Author of original report
Thu, September 25, 2003
Tony's Formula to calculate dirt delivered Actual House pad size measured: 100' on 2 sides, 98' 3rd side and 87' an 4th side 6.5' high 100x100x6.5 divided by 2 =32,500 cubic feet 87x98x6.5 divided by 2 = 27,710 cubic feet 32,500+27,710 = 60,210 cubic feet 60,210 cubic feet divided by 27 (to convert to cubic yards)= 2230 cubic yards 2230 cubic yards divided by 18 yds (to convert to truck loads)= 124 truck loads 124 truck loads X 30% for compaction loss = 37 truck loads 124 + 37 = 161 truck loads needed to build Actual House Pad 100 on 2 sides 98 and 87 on remaining sides Tony claimed he delivered 184 truck loads, i had another 60 truck loads delivered, thats a total of 244 truck loads of fill lets take off for his 20 loads spread out over my lot, 224 loads and the house pad was not even the correct size