Dover pa. john
Dover,#2Author of original report
Wed, August 05, 2009
In April of 09 Mr. Ross contacted me and stated he would be coming out to redo the work. Then again in May and June and July. Finally on July 23rd he dropped of the excavator to do the work. Then he didn't show. The equipment sat idle. On 8/3/09 I contacted Mr. Ross. He gave me the same old line about not getting paid for others job. ( I've paid him in full). I asked please don't pull your equipment so I know it's going to get done. He told " I won't". When I got home on the evening of 8/5/09 the equipment was gone. I was furious. When I reached Mr. Ross in the morning the next day I was told the machine was needed to a septic job. He also voiced displeasure that I've called him out in the forum. I don't see that as my problem. I paid for a service and product that he willing admits is wrong and needs to be changed. However, it still remains a shambles.